监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 甲方项目管理系统 | 签约案例 | 客户案例 | 在线试用
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

2010年PMP美国项目管理考试习题及答案三十一

申请免费试用、咨询电话:400-8352-114

QUEST Network schedules are prepared during the _____ phase and updated during the _____ phase. 
A Conceptual, execution. 
B Development, implementation. 
C Development, close-out. 
D Implementation, close-out. 
E Planning, finishing. 
参考答案:B

QUEST Scheduling systems such as PERT, ADM, and PDM are project management tools to be used by: 
A The project manager and project office personnel. 
B The project team  and functional managers. 
C The project sponsor. 
D All of the above. 
E A and B only. 
参考答案:E

QUEST Increasing resources on the critical path activities may not always shorten the length of the project because: 
A Certain activities are time-dependent rather than resource-dependent (i.e., using three ovens rather than one to bake a cake). 
B Safety, OSHA and EPA may have placed restrictions on the number of people used on certain activities or in the physical location of the project. 
C The skill level of the added resources might not be appropriate for the activities to be performed. 
D Adding more resources may create additional work and produce inefficiencies (i.e., additional people may need training and supervision.) 
E All of the above. 
参考答案:E

QUEST A line manager provides you with three estimates for his activity in your PERT network.  His estimates are 2 weeks optimistically,  4 weeks most likely, and 12 weeks pessimistically.  The expected time which would appear on the chart would be: 
A 4 weeks 
B 5 weeks 
C 6 weeks 
D 7 weeks 
E None of the above. 
参考答案:B

QUEST Management has decided to "crash" a project in order to avoid penalty payments for late deliveries.  To crash the project, either overtime or additional resources should be assigned to: 
A All activities. 
B Only those activities with the longest time durations. 
C Those activities on the critical path begining with the longest time duration activities. 
D Those activities with the greatest degree of risk. 
E None of the above. 
参考答案:C

相关试题:

2010年PMP美国项目管理考试习题及答案三十

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:55    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件