2010年PMP美国项目管理考试习题及答案三十

申请免费试用、咨询电话:400-8352-114

QUEST The first step in building a PERT/CPM network is to: 
A Create a flow chart 
B Determine the critical path 
C Show task relationships 
D Create a work breakdown structure 
E None of the above. 
参考答案:D

QUEST The critical path in a schedule network is the path that: 
A Takes the longest time to complete 
B Must be done before any other tasks 
C Allows some flexibility in scheduling a start time. 
D Is not affected by schedule slippage 
E All of the above. 
参考答案:A

QUEST Assume that you have a network where an activity on the critical path can be crashed by two weeks.  If the activity is actually crashed by two weeks, then: 
A The project's schedule will be reduced by 2 weeks. 
B The available slack on the noncritical paths will increase. 
C A new critical path may appear after the crash. 
D All of the above. 
E A and B only. 
参考答案:C

QUEST Your team has prepared a CPM schedule for your review.  You notice that one node has six inputs (including two dummy activities) and four outputs (which include one dummy activity).  Select the correct statement from the following: 
A This is a valid representation if the logic is correct. 
B This is invalid because a node can have a maximum of one dummy input representation if the logic is correct. 
C This is invalid because nodes cannot have both dummy inputs and dummy outputs. 
D This is a invalid because the number of outputs must equal the number of inputs. 
E This is invalid because a maximum of two inputs and two outputs are allowed using the critical path method. 
参考答案:A

QUEST During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule.  The baseline schedule: 
A Now becomes the new schedule, including the changes, and the original baseline is disregarded. 
B Is still the original baseline but annotated to reflect that a change has taken place. 
C Is amended to reflect the scope change, but the original baseline is still maintained for post-project review. 
D Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.) 
E Is the same since baseline schedules cannot change once the development phase is completed. 
参考答案:C

相关试题:

2010年PMP美国项目管理考试习题及答案二十九

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:55    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件