QUEST Using the figure in the Special window,  Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks. 
A 11, 13 
B 12, 14 
C 13, 15 
D 14, 16 
E 15, 17 
参考答案:E

QUEST Using the figure in the Special window,  The Critical path is _____ weeks. 
A 21 
B 22 
C 23 
D 24 
E 25 
参考答案:D

QUEST Using the data shown in the Special window,  Activities P, Q, and T are critical path activities.  In order to shorten the time duration of the project, which activity should be "crashed" first? 
A P 
B Q 
C R 
D S 
E T 
参考答案:A

QUEST Using the figure in the Special window,  By how many weeks can activity "F" slip without extending the end date of the project? 
A 0 
B 1 
C 2 
D 3 
E 4 
参考答案:D

QUEST Using the figure in the Special window,  The critical path is: 
A A-B-G 
B C-G 
C C-D 
D E-F 
E A-B-G and C-D 
参考答案:B

相关试题:

2010年PMP美国项目管理考试习题及答案二十八

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:55    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件