监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 甲方项目管理系统 | 签约案例 | 客户案例 | 在线试用
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

2010年PMP美国项目管理考试习题及答案六

申请免费试用、咨询电话:400-8352-114

QUEST The scope of a project can be expected to change if:
A The project manager must provide cost estimates without having a design concept
B Oversimplification (underestimating) of the nature of the work occurs
C The project manager is assigned after the project is defined, and the cost and schedule are approved
D A clear objective is not provided
E All of the above are possible based upon the situation
参考答案:E

QUEST The most common non-behavioral reason for projects being completed behind schedule and over budget is:
A Selecting the wrong person as the project manager
B Selecting the wrong person as the sponsor
C Accepting a high-risk project
D Ill-defined requirements
E All of the above
参考答案:D

QUEST The appointment or selection of a project sponsor is often based upon:
A The strategic importance of the project
B Who the customer is
C Whether the organization is project or non-project-driven
D The profitability of the project
E All of the above
参考答案:E

QUEST The "rolling wave" or "moving window" concept is used most frequently on projects where:
A The baseline is frozen for the duration of the project and no scope changes are permitted
B Marketing is unsure of what the customer actually wants and reserves the right to make major scope changes
C The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work
D Networking techniques are not appropriate
E All of the above
参考答案:C

QUEST Interfacing with the customer after project go-ahead is the responsibility of:
A Project sponsor
B Project team
C Project manager
D Functional manager
E All of the above are possible, based upon the size and complexity of the project
参考答案:C

试题推荐:

2010年PMP美国项目管理考试习题及答案一

2010年PMP美国项目管理考试习题及答案二

2010年PMP美国项目管理考试习题及答案三

2010年PMP美国项目管理考试习题及答案四

2010年PMP美国项目管理考试习题及答案五

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:55    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件