2010年PMP美国项目管理考试习题及答案四

申请免费试用、咨询电话:400-8352-114

QUEST We assign human and non-human resources in the _____ phase of the budget.
A conceptual
B planning
C development
D implementation
E close-out
参考答案:D
QUEST Project trade-offs vary between
A risk, cost and schedule.
B direct cost, indirect cost, and resource availability
C quality, schedule and time
D cost, quality and schedule
E contract terms, scope and budget
参考答案:D
QUEST The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.
A budget, schedule
B quality requirements, schedule
C size, type of industry
D nature, size
E project manager, sponsor
参考答案:D
QUEST The time necessary to complete a project is called the _______ of a project.
A Implementation Time
B Life Cycle
C Operation Time
D Critical Path
E Completion Phase
参考答案:B
QUEST When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the
A task
B level of effort
C sub-task
D project
E work package
参考答案:E

试题推荐:

2010年PMP美国项目管理考试习题及答案一

2010年PMP美国项目管理考试习题及答案二

2010年PMP美国项目管理考试习题及答案三

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:55    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件