QUEST Work packages are used to: 
A Represent units of work at a level where work is performed. 
B Clearly distinguish one work package from all others assigned to a single functional group. 
C Limit the work to be performed to relatively short periods of time. 
D All of the above. 
E A and B only 
参考答案:D

QUEST Project life cycles are very useful for _____ and _____ . 
A Configuration management, termination 
B Objective setting, information gathering 
C Standardization, control 
D Configuration management, weekly status updates 
E Approval, termination 
参考答案:C

QUEST Which of the following are included as part of a scope statement? 
A Project justification 
B Project deliverables 
C Project objectives 
D All of the above 
E B and C 
参考答案:D

QUEST The initial document that formally recognizes the existence of a project is the _____ . 
A Scope baseline 
B Management plan 
C Project charter 
D Configuration control report 
E None of the above 
参考答案:C

QUEST Which of the following is not a scope management process? 
A Initiation 
B Scope planning 
C Scope Definition 
D Scope change control 
E Scope verification 
参考答案:D

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:55    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件