2009年项目管理PMP模拟考试习题(4)
小编推荐:
2009年项目管理PMP模拟考试习题(3)
31. You are evaluating a change to the project and trying to decide whether to lease or buy an item for the project. The daily lease cost is US $240. The cost of purchasing the item is US $6,800 for the investment cost and US $70 for the daily cost. How long will it take the lease cost to equal the purchase cost?
A.30 days.
B.40 days.
C.50 days.
D.60 days.
你正在评估对项目的一项变更,并争取决定是租赁还是购买项目用的一台设备。该设备的日租赁费为240美元,购买该设备的费用为6,800美元投资成本,70美元的日成本。需要多长时间租赁成本才能等于购买成本?
A.30天
B.40天
C.50天
D.60天
32. An employee approaches you and asks if he can tell you something in confidence. He advises you that he has been performing illegal activities within the company for the last year. He is feeling guilty about it and is telling you to receive advice as to what he should do. What should you do?
A.Ask for full details.
B.Confirm that the activity is really illegal.
C.Inform your manager of the illegal activity.
D.Tell the employee to inform their boss.
一个雇员靠近你问,他是否可以告诉你一些秘密。他告诉你,去年他一直在公司内进行非法活动。他现在对此感到内疚,并请你建议他怎样做。你应该怎样做?
A.问他详细情况
B.确认他的活动是否真的非法
C.把这种非法活动通知你的经理
D.让这个雇员去通知他的上司
33. All of the following are required to bring a project to closure EXCEPT?
A.Perform project feedback with the team.
B.Obtain sign off from the customer.
C.Review project documentation for completeness.
D.Update the project plans.
对一个项目进行收尾,下列哪项是不需要的?
A.与团队实施项目反馈
B.获得客户的终止签字
C.审核项目竣工文件
D.更新项目计划
34. The sponsor wants the project completed in 40 days. The CPI is 1.1, the project critical path duration is 38 days with a standard deviation of two days. What is the maximum project float?
A.Zero days.
B.Two days.
C.Four days.
D.Six days.
项目发起人想让项目在40天内完成。CPI为1.1, 项目关键路径历时为38天,标准偏差为2天。项目的最大浮动时间是多少?
A.0天
B.2天
C.4天
D.6天
35. Which type of organizations BEST for managing complex projects involving cross-disciplinary efforts?
A.Projectized
B.Functional
C.Line
D.Matrix
管理涉及专业交叉作业任务的复杂项目, 下列哪种组织形式是最佳的?
A.项目型
B.职能型
C.直线型
D.矩阵型
36. While completing a project, a project manager realizes he needs to decrease projects. After researching his options, he comes up with the following choices. Which choice would DECREASE project costs?
A.Change to component A from component B.component A costs more to purchase but has a lower life-cycle cost than B.B.Change task A to be completed by resource B instead of resource C.Resource B is a more experienced worker.
C.Move tasks B and H to occur concurrently, and take the risk of a 30% increase in the need for five more resources later.
D.Delete an acceptance test from the project plan.
当进行一个项目时,项目经理意识到他需要减少项目的费用。在研究了他的选项后,他得出下列选择项。哪项将减少项目的费用?
A.从成分B转变为成分A,成分A的采购费用比成分B高,但生命周期费用比成分B低。
B.把负责完成任务A的资源C改为资源B。资源B是一名经验更丰富的工人。
C.移动任务B和H使它们同时发生,并承担以后增加30%需要另外5个资源的风险。
D.从项目计划中删除验收检验。
37. During the execution of a project, the project manager determines that a change is needed to material purchased for the project. The project manager calls a team meeting to plan how to make the change. This action is an example of:
A.Management by objectives.
B.Lack of a change control system.
C.Good team relations.
D.Lack of a clear work breakdown structure.
在一个项目的实施中,项目经理确定项目所采购的材料需要一项变更。这个项目经理召集了团队会议,对如何进行变更做出计划。这种行动是:
A.通过目标进行管理。
B.缺乏变更控制系统。
C.良好的团队关系。
D.缺乏清晰的工作分解结构。
38. A Roles and Responsibility Matrix is mostly used in projects in order to:
A.Allocate tasks to team members
B.Define Stakeholders interests and roles
C.Allocate responsibilities to key team members and other parties for key activities or deliverables
D.Ensure quality of deliverables
在项目中通常使用任务职责矩阵,主要是为了:
A.给团队成员分配任务
B.界定项目干系人的利益和角色
C.确定关键团队成员职责以及其他人员要完成的关键活动和可交付成果
D.确保可交付成果的质量
39. In which of the following forms of organization do projects receive the LEAST attention?
A.Functional
B.Matrix
C.Expeditor
D.Coordinator
下列哪种组织形式使项目得到最少的关注?
A.职能型
B.矩阵型
C.稽查员型
D.协作型
40. You just completed a cost estimate on the project, and you’re assuming there’s a 15% chance you will exceed this estimate. You are:
A.Below the mean.
B.Above the mean.
C.Above the median.
D.Below the median.
你刚刚完成关于项目的一项成本估算,并且你假设超出估算的机会为15%。那么,你是:
A.低于平均值
B.高于平均值
C.高于中间值
D.低于中间值
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1基坑放坡开挖应符合规定
- 2[北京]商业广场施工现场平面布置图(基础、主体、装修)
- 3【招标师考试】项目管理与招标采购第三章:国际贸易惯例的特征
- 42015招标师考试科目法律法规:机电产品国际招标
- 5招投标重整“上层建筑”
- 6一级建造师管理与实务复习要点:抗震等级和耐火等级
- 7江苏苏州启动农村污水治理计划
- 82013年二级建造师《施工管理》每日一练(12.6)
- 92015年咨询工程师《工程咨询概论》每日一练11.22
- 10[深圳]首个城中村异地安置项目 政府依法清拆
- 11工程咨询概论知识点:注册咨询工程师权利与义务
- 12绍兴公布2015安全工程师报名时间:6月16日至25日
- 13浇注聚氨酯硬泡外墙外保温工程施工工艺
- 14基坑支撑结构的概述
- 15山西:实现高速公路建设史上创举
- 16一级建造师管理与实务复习要点:钢筋代号
- 1716m先张法预应力空心板施工方法
- 18《工程项目组织与管理》:工作定义的成果
- 19安全工程师考试《生产管理》模拟题(12)
- 20PMP认证考试练习题及参考答案(四十五)
- 21安全工程师安全生产法复习资料——有关政府、部门工作人员
- 22信息系统监理变更控制的八项基本原则
- 232015年惠州安全工程师考试报名时间为4月26日-5月20日
- 24建筑施工项目的信息化管理
- 25某医院迁建改建项目给排水工程技术方案 185p
- 262015年造价工程师考试《计价控制》第二章知识(5)
- 27砖混结构基础设计技巧
- 282015二级建造师《建筑》:荷载的分类
- 29安全工程师《法律法规》习题班讲义精选(96)
- 30污染场地土壤修复技术导则(征求意见稿)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼