PMP项目管理:项目集成管理练习题1
A.A sense of ownership and belonging
B.A detailed project plan
C.Direction and leadership
D.Common objectives
授权给项目团队要求项目经理提供下列事项但除了
A.拥有和归宿感
B.详细的项目计划
C.指挥和领导
D.共同的目标
2.Project managers spend a considerable amount of time communicating and interacting with project stakeholders.Which of the following methods or techniques would be most useful for a project manager to keep the project team focused on project success?
A.Analyze the work occasionally to determine what can be eliminated
B.Keep the priorities clear
C.Schedule the most interesting activities at energy peaks
D.When problems arise, transfer blame to the stakeholders
项目经理要花很多时间与项目相关者进行沟通交流下列哪项方法或技术会对项目经理最有用以便项目团队齐心协力使项目成功
A.定期分析工作以决定排除什么事项
B.明确优先事项
C.在精力高峰期安排最有趣的活动
D.当出现问题时责备其它项目相关者
3.A project sponsor is required to make important decisions that may impact the future of the project.In helping the sponsor to arrive at good decisions, the project manager should
A.Withhold information that may be embarrassing to the team or senior management
B.Have a wide variety of graphs and table available
C.Utilize progress charts with current week’s information only
D.Provide timely, accurate and complete data on a regular basis
事关项目未来成败的重要决策要由项目业主决定为了帮助业主作出明智决策项目经理应该
A.隐瞒可能会让项目团队或高层管理难堪的信息
B.充分准备各种图表
C.使用仅表明本周信息的进度图表
D.定期规范地提供准确完整及时的数据资料
4.A project manager estimates a project will take 14 weeks at a cost of $60,000.In signing the contract documents, the customer imposes a penalty for late completion of $2,000 per estimates that the maximum possible crashing of the project duration is 4 weeks, at an additional cost of $9,000.Assuming that the project manager is going to make the decision and that cost is the driving criteria for the project manager’s organization, what is the expected project cost?
A.$69,000
B.$71,000
C.$70,000
D.$62,000
某项目经理估算一项目要花14 周时间成本$60,000 在签合同文件时客户要求延期完工赔偿$2,000 项目工期的最大可能的赶工时间是4 周附加成本$9,000 假定成本是主要的衡量标准项目经理要作出决策什么是预期的项目成本
A.$69,000
B.$71,000
C.$70,000
D.$62,000
5.All of the following processes are part of over all Project Integration Management, except:
A.Project Plan Execution
B.Project Plan Development
C.Schedule Control
D.Integrated Change Control
下列事项是整个项目综合管理的一部分除了
A.项目计划执行
B.项目计划开发
C.进度控制
D.整体变化控制
6.Core planning processes have clear dependencies that require them to be performed in essentially the same order on most projects.Which of the following is the correct order as a portion of core planning processes?
A.Scope planning, scope definition, activity sequencing, activity duration estimation
B.Scope definition, scope planning, activity definition, activity sequencing, activity duration estimation
C.Scope planning, scope definition, activity sequencing, activity definition, activity duration estimation
D.Activity duration estimation, scope planning, scope definition, activity definition, activity sequencing
核心计划过程有明确的依赖关系在大多数项目中要以同样的顺序必须完成下列哪一项符合核心计划过程的正确顺序.
A.范围规划--范围定义--活动排序--活动工期估计
B.范围定义--范围规划--活动定义--活动排序--活动工期估计
C.范围规划--范围定义--活动排序--活动定义--活动工期估计
D.活动工期估计--范围规划--范围定义--活动定义--活动排序
7.In which project life cycle phase is uncertainty associated with project integration usually the greatest?
A.Project executing
B.Project planning
C.Project closeout
D.Project approval
在项目生命周期哪一阶段项目整合的不确定性最大
A.项目执行
B.项目规划
C.项目收尾
D.项目审定
8.In making key changes to a project, it is important to have a formal change process and a ____________ responsible for approving or rejecting requests.
A.Stakeholder
B.Change control board
C.Subject matter expert
D.Project manager
在项目作出重要变更时重要的是要有一个正式的变更过程和一个负责批准或拒绝变更要求的
A.项目相关者
B.变更控制委员会
C.领域事务专家
D.项目经理
9.In which project life cycle phase are the risks associated with project integration usually the smallest?
A.Project initiation and approval
B.Project planning
C.Project execution D.Project closeout
在项目生命周期哪一阶段项目整合的风险最小
A.项目立项和审定
B.项目规划
C.项目执行
D.项目收尾
10.The most encompassing document to help the project team with project integration activities is the _________.
A.Project charter
B.Project plan
C.“As built” report
D.Scope change control procedure
能帮助项目团队进行项目整合活动的最完整的文件是
A.项目章程
B.项目计划
C.进程报告
D.范围变更控制流程
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 12015年招标师:招标采购专业实务精选习题13
- 2朝阳市2015年安全工程师考试报名时间为5月15日至6月15日
- 32014版《建设工程司法鉴定程序规范》适用范围
- 42015年一级建造师机电工程:特种作业人员管理
- 52015年一级建造师《工程经济》第一篇冲刺讲义(3)
- 6哈尔滨银行大厦工程开工
- 72015年安全工程师考试《安全管理知识》:紧急情况
- 8软件项目管理在农房建设质量安全隐患多的原因是什么?
- 9锚杆拉杆有哪些组装与安放方法?
- 102015年咨询工程师《政策与规划》每日一练(5.14)
- 11一级建造师法规及相关知识复习要点:质量责任义务
- 12一级建造师管理与实务复习要点:不可抗力损失
- 13节理按力学性质分类分为哪些?
- 14有趣的造价现象
- 15江西抚州市2013年重大项目推进调度会召开
- 16造价工程师建设工程造价管理复习资料——价值功能的特点
- 172013年重庆二级建造师注册证书、执业印章遗失补办申请表
- 18二建复习资料隐蔽工程的验收
- 192020年江西铁路里程将突破5000公里
- 20混凝土输送泵管安装技巧
- 21新疆2015年度造价工程师考试报名时间为6月10日-7月10日
- 22一级建造师市政公用工程管理与实务:盖挖顺作法
- 23山西:11月全省重点工程建设保持良好态势
- 24二级建造师考试备考四步制胜秘笈
- 252015年咨询工程师考试《分析与评价》:建设方案设计的作用
- 26[广东]06年注册安全师考试网上成绩查询
- 27造价工程师技术与计量(土建)复习资料——板材隔墙
- 28工程造价基础知识合同概述:合同的订立
- 292015年招标师《招标采购法律法规与政策》试题(9)
- 302015年安全工程师《安全生产法及相关法律知识》每日一练(3.1)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼