PMP美国项目管理认证的模拟考试的样题10
The _____ is for (usually major) scope changes that were
not considered as part of the original plan, whereas the
_____ is to compensate for minor changes in estimating,
escalation factors.
A. Management reserve, unplanned allowance fund.
B. Management reserve, contingency.
C. Contingency fund, management reserve.
D. Unplanned allowance fund, budgetary reserve.
E. Unplanned reserve, planned reserve.
ANS: C
2. To determine what causes the majority of quality
problems in a process, a very useful tool is the:
A. cause and effect diagrams.
B. flow chart.
C. control chart.
D. pareto chart.
E. trend chart.
ANS: D
3. Which of the following is not part of contract
administration
A. contract award
B. performance control
C. financial control
D. contract closeout
E. All of the above are parts of contract
administration.
ANS: A
4. A(n) _____ system is designed to ensure the timely
availability of nonhuman resources, and includes the
cost in procurement, shipping/freight, storage and loss.
A. Inventory control.
B. Materials management.
C. Procurement.
D. All of the above.
E. A and C only.
ANS: B
5. Expectancy theory as applied to project management
implies that:
A. The team will work the hardest on those goals that
are clearly explained by the project manager
B. The more rewards that the project manager provides,
the better the performance of the team
C. Team members will work hardest for those project
goals that also bring satisfaction to personal goals
D. Employees will work hardest for those project goals
which are accompanied by high levels of authority for
the individual team members
E. None of the above
ANS: C
6. Non-verbal communication includes:
A. Body movement
B. Gestures
C. Facial expressions
D. The way we move our hands
E. All of the above
ANS: E
7. The formal invitation to submit a price for specified
goods/services is usually referred to as:
A. request for proposal
B. request for quotation
C. tender invitation
D. bid invitation
E. A and B only
ANS: B
8. The project scope/charter baseline includes:
A. Summary of background conditions defining the
project.
B. Organization, authority and responsibility
relationships.
C. Functions to be performed.
D. Resource requirement schedule including time
estimates.
E. All of the above.
ANS: E
9. Which of the following is not an input to quality
planning?
A. scope statement.
B. regulations.
C. work results.
D. standards.
E. quality policy.
ANS: C
10. Which of the following networking methods allows
us to show that the last 10% of one element cannot be
completed until 62% of a previous element has been
completed?
A. PERT
B. ADM
C. PDM
D. All of the above.
E. A and C only.
ANS: C
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1古香道园林工程投标施工组织设计104p
- 22015招标师考试:招标采购专业实务详解30
- 3某广场室外景观工程广场铺装标段(投标书)
- 42015年咨询工程师《工程项目组织与管理》每日一练4.29
- 5杭南长客运专线明年通车 南昌到长沙只需1.5小时
- 62015注册安全工程师考试考前冲刺试题精选(12)
- 7现浇混凝土有网聚苯板外保温施工工艺
- 8高速公路特长隧道深大竖井施工工法
- 9建筑安全员主要工作内容
- 10造价工程师技术与计量(建筑)复习要点:天棚与吊顶
- 112015年招标师考试:招标实务问答(十九)
- 122015年二级建造师《法规及相关知识》解题技巧(五)
- 13某医院污水处理设计方案 33p
- 142015年监理工程师《基本理论和相关法规》练习题(96)
- 152015一级建造师《市政工程》知识点摘要(6)
- 162012一级建造师《项目管理》:施工安全控制
- 17排水管道施工组织方案18P
- 18天津某超高层酒店平面布置图汇编
- 19招标师真题答案
- 20二级建造师法规知识点:委托合同的法律特征
- 21商丘市开展农村危房改造工作专项督查
- 22某五星级酒店电气施工组织设计
- 23厦门东通道(翔安隧道)项目隧道主体工程某标(实施)施工组织设计
- 24安全工程师答疑精华:当教材和讲义不相同
- 25《项目管理与采购》重点知识:建设系统招标要求
- 262015年一级建造师《法规》:合同法(1)
- 27克塔高速公路特大桥架设完成
- 28安全工程师生产管理复习要点:五类高危行业
- 29一级建造师《工程经济》考点:设备租赁与购置方案分析
- 302015招标师《法规与政策》考前知识点:开标参与人
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼