PMP美国项目管理认证的模拟考试的样题7
following phase of the project:
A. conceptual
B. execution
C. cut-over
D. post project evaluation
E. A and D only
ANS: A
2. The most common types of schedules are Gantt charts, milestone charts, line
of balance, and:
A. Networks.
B. Time phased events.
C. Calendar integrated activities.
D. A and C only.
E. B and C only.
ANS: A
3. Which of the following is often overlooked in achieving effective
communication?
A. speaking clearly
B. listening
C. interpreting
D. maintaining eye contact
E. manipulating the conversation
ANS: B
4. Which type of contract requires that the buyer keep the tightest
labor/material cost control?
A. Cost Plus Incentive Fee
B. Cost Plus Percentage of Costs
C. Cost Plus Fixed Fee
D. Firm Fixed Price
E. Firm Fixed Price Plus Incentive
ANS: B
5. A task-oriented family tree of activities is a:
A. Detailed plan.
B. Linear responsibility chart.
C. Work breakdown structure.
D. Cost account coding system.
E. Work package description.
ANS: C
6. Adding 5 people to a 4 person team increases the communication channels by a
factor of:
A. 2 times
B. 3 times
C. 4 times
D. 5 times
E. 6 times
ANS: E
7. Cost management includes:
A. Cost estimating/forecasting.
B. Cost budgeting/cost control.
C. Cost applications.
D. All of the above.
E. A and B only.
ANS: D
8. Participative Management:
A. involves the solicitation of information from all team members.
B. assumes that members avoid work and responsibility.
C. suggests the sharing of power and decision making.
D. employs a Theory X style of leadership.
E. A and C
ANS: E
9. The auditing function that provides feedback about the quality of output is
referred to as:
A. quality control.
B. quality planning.
C. quality assurance.
D. quality improvement
E. All of the above.
ANS: C
10. The lowest dollar amount ’at stake’ is associated with the following phase
of the project:
A. conceptual
B. execution
C. cut-over
D. post project evaluation
E. A and D only
ANS: A
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 12015咨询工程师《工程咨询概论》练习题32
- 2造价工程师技术与计量复习要点:泵送混凝土
- 3承德市2015年安全工程师考试报名时间确定:4月22日至5月14日
- 4构思、预控、创新,努力提高装饰工程质量
- 5广乐高速大瑶山段一号隧道右线贯通
- 62015年注册监理工程师《案例分析》高分突破(一)
- 7湖北:基本形成高速公路“四纵四横一环”主骨架
- 82015年二级建造师:轻松记住二级建造师难点问题
- 92015年招标师:投标文件的送达和签收
- 102015招标师考试教材《法规与政策》:第五章5
- 112015年安全工程师生产技术练习(4)
- 12投标人信誉
- 13混凝土泵对端部橡胶输送软管的要求
- 142015年造价工程师考试《计价控制》第二章知识(3)
- 15全国监理工程师2015年考试《合同管理》习题(4)
- 16某中学迁扩建工程施工进度总网络计划
- 172015年造价工程师考试土木工程复习资料—筒体结构
- 18做好加油站雨季安全的几点注意事项
- 192015年咨询工程师《工程项目组织与管理》每日一练(10.21)
- 20工程师只批准工期顺延而不给经济补偿的有哪些
- 21不方便放坡时的最小降水深度
- 22西藏:“十二五”期间改建农村公路3.3万公里
- 232015年咨询工程师《宏观经济政策与发展规划》每日一练6.25
- 24造价工程师案例分析复习要点:关于调整所得税
- 25一级建造师管理与实务复习要点:招标控制价
- 262015年二级建造师《施工管理》每日一练(2.18)
- 27断面岩石掘进机在困难地层中的施工
- 282015年招标师《项目管理与招标采购》考前提高试题19
- 29【招标师考试技巧】:有效掌握考点
- 30连云港公布2015安全工程师报名时间:6月15日—6月21日
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼