assembly lines commonly include:
A. a directing style of leadership.
B. a lack of confidence in their workers
C. assumption that workers lack ambition and dislike responsibility
D. a Theory X style of leadership
E. All of the above.
ANS: E
2. Quality management:
A. is another name for careful inspections.
B. is inversely related to productivity.
C. is primarily the responsiblity of management.
D. is primarily the responsibility of the workers.
E. is essentially a motivational technique.
ANS: C
3. Risk management allows the project manager and the project team
to:
A. eliminate most risks during the planning phase of the project
B. identify project risks
C. identify impacts of various risks
D. plan suitable responses
E. B, C and D only
ANS: E
4. Scheduling is the process by which decisions are made concerning:
A. Tasks to be accomplished.
B. Personnel/organization that will be assigned to accomplish the
task.
C. Time when the tasks are to be completed.
D. All of the above.
E. A and C only.
ANS: E
5. The basic elements of communication include:
A. Listening, talking and sign language.
B. Communicator, encoding, message, medium, decoding, receiver, and
feedback
C. Clarity of speech and good listening habits
D. Reading, writing and listening
E. All of the above
ANS: B
6. Which of the following would most likely increase the accuracy of
estimating the project cost?
A. Pricing out the work at lower levels in the work breakdown
structure.
B. Using historical data.
C. Talking to people who have worked on similar projects.
D. All of the above.
E. A and C only.
ANS: D
7. A variance envelope has been established on a project. The
envelope goes from +-30% in R&D to +-5% during manufacturing. The
reason for
the change in thickness of the envelope is because:
A. The management reserve has been used up.
B. The accuracy of the estimates in manufacturing are worse than the
estimates in R & D.
C. Tighter controls are always needed as a project begins to wind
down.
D. Of the personal desires of the project sponsor.
E. Of none of the above
ANS: E
8. Cost of quality is:
A. associated with non-conformance to specifications and
requirements.
B. primarily caused by poor workmanship of workers who are building
or manufacturing the product.
C. used to determine whether a quality management program is suitable
for a given project.
D. negligible for most large projects.
E. A and B
ANS: A
9. Management plans include all of the following except:
A. Organization of project.
B. Job descriptions.
C. Policies and procedures.
D. Linear responsibility charts.
E. Scope baseline.
ANS: E
10. The Japanese resource management model exhibits:
A. a cooperative spirit of goal setting.
B. non-specialized career paths
C. frequent changes in team assignments
D. a Theory Z style of management
E. All of the above.
ANS: E
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1最大核电规划项目开工 核电重启
- 2路堑客土喷播植草施工方案23p
- 3招标师职业水平考试:项目管理与招标采购第二章练习题33
- 4安全工程师生产管理复习要点:径集数
- 52015年咨询工程师《决策分析与评价》模拟题(15)
- 6未列入合同文件的地质资料使用问题
- 72015年贵州安全工程师考试报名时间为6月1日-6月21日
- 8某驳岸围堰专项施工方案
- 9江西省关于2015年度造价师网络教育收款收据换取发票的通知
- 10《项目管理与招标采购》辅导:项目进度管理体系
- 11安全工程师案例分析复习要点:火灾
- 12建设工程施工全过程安全监理
- 13灌注水下混凝土时钢筋笼上升的预防及处理
- 142015年一级建造师《通信与广电》知识摘要(11)
- 152015年造价工程师《理论与法规》课程讲义(5)
- 16引水隧洞施工组织设计84p
- 17金沙江鲁某水电站保通隧道工程施工组织设计
- 182015年宁夏注册安全工程师报名入口
- 192015招标师成绩:法规81、管理85、实务76、案例74
- 202015年齐齐哈尔造价工程师现场审核地点及时间
- 21小型混凝土搅拌车驱动装置的维护工作
- 222015安全工程师《生产管理知识》试题精选(2)
- 232015年咨询工程师《宏观经济政策》练习题(50)
- 242015年一级建造师考试《法规及相关知识》冲刺习题(13)
- 25某公园水景工程施工组织设计
- 262015造价员《土建工程》知识点:防水涂料
- 272015年安全工程师考试《安全生产法及相关》辅导资料(25)
- 282012一级建造师《机电工程》焊接材料的分类
- 29普通碳素结构钢进场外观检查的内容是什么
- 30招标师考试:项目融资风险管理
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼