PMP美国项目管理认证的模拟考试的样题6
A. an exchange of information.
B. providing written or oral directions.
C. consists of senders and receivers
D. effective listening.
E. All of the above
ANS: E
2. Fixed Price contracts place more risk on the:
A. owner
B. buyer
C. seller
D. contractor
E. C or D
ANS: E
3. Life cycle costing is the total cost to the customer for the acquisition and
ownership over its full life. Life cycle costing categories include the cost
of _____, _____, and _____.
A. R & D, maintainability, operation and support.
B. R & D, production, operation and support.
C. Acquisition, operations, maintenance.
D. Production, operations, maintenance.
E. None of the above
ANS: B
4. Management By Objectives assumes that the team:
A. is receptive to an unstructured environment.
B. does not require close supervision.
C. possesses a self directed philosophy
D. identifies with project objectives.
E. All of the above.
ANS: E
5. Quality may be defined as:
A. conformance to requirements.
B. fitness for use.
C. continuous improvement of products and services
D. appeal to the customer
E. All of the above except B
ANS: E
6. Since risk is associated with most projects, the best course of action is
to:
A. cover all project risks by buying appropriate insurance
B. ignore the risks, since nothing can be done about them and move forward with
the project in an expeditious manner.
C. avoid projects with clear and present risks
D. eliminate all known risks prior to the execution phase of the project
E. identify various risks and implement actions to mitigate their potential
impact
ANS: E
7. The process of choosing/documenting the best approach to achieve the project
objectives is part of:
A. The scope baseline.
B. Scope authorization
C. Scope definition
D. Scope planning.
E. All of the above.
ANS: D
8. Time management is the allocation of time in a project’s life cycle through
the process of:
A. Planning
B. Estimating.
C. Scheduling.
D. Controlling
E. All of the above.
ANS: E
9. A comprehensive definition of scope management would be:
A. Managing a project in terms of its objective through the concept,
development, implementation, and termination phases of a project.
B. Approval of the scope baseline.
C. Approval of the detailed project charter.
D. Configuration control.
E. Approved detailed planning including budgets, resource allocation, linear
responsibility charts and management sponsorship.
ANS: A
10. Cost Plus Percentage of Cost contracts are more desirable for the:
A. owner
B. buyer
C. seller
D. contractor
E. C or D
ANS: E
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1如何推进项目管理信息化
- 2河流有哪些下蚀作用?
- 32015年监理工程师三控选择第41-50题
- 4立柱化学植筋加固方法
- 5海航集团利用统一门户技术实现综合信息管理
- 62015咨询工程师考试《咨询概论》预测试题(10)
- 72015年咨询工程师《工程咨询概论》每日一练(12.26)
- 8范围管理:公路桥梁引道不均匀沉陷防治措施的初探
- 9启动2009年度招标师再登记工作通知
- 102015年造价工程师《理论与法规》教材讲解(5)
- 11铁路隧道施工组织设计范文(实施)
- 122015年咨询工程师《工程咨询概论》每日一练(4.5)
- 13招标师考试《招标采购案例分析》资料(4)
- 142015年二级建造师《施工管理》每日一练(11.07)
- 15施工项目管理部 内容
- 16特殊人员是包含在特种作业人员里的吗
- 17北京某框剪教学楼防水工程施工方案
- 18《政策与发展规划》知识点:政策性银行
- 19裸露爆破法安全技术
- 202015年监理工程师《建设工程合同管理》练习题(19)
- 21厨房卫生间地面聚合物水泥防水涂料施工工艺
- 22造价工程师复习资料:概算指标的作用
- 232013年西藏二级建造师初始注册申请表
- 24二级建造师《法规》考点狂背:施工安全生产许可证制
- 25自来水厂及管道施工组织设计204P
- 26监理工程师考试2015《建设工程合同管理》练习题(8)
- 272015年招标师考试:招标实务问答(84)
- 28软件项目管理与一般项目管理的区别是什么?
- 29【经验之谈】二级建造师行业的前景及待遇怎么样?
- 302015年咨询工程师《宏观经济政策与发展规划》每日一练(8.19)
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼