PMP美国项目管理认证的模拟考试的样题4
A. an exchange of information.
B. providing written or oral directions.
C. consists of senders and receivers
D. effective listening.
E. All of the above
ANS: E
2. Fixed Price contracts place more risk on the:
A. owner
B. buyer
C. seller
D. contractor
E. C or D
ANS: E
3. Life cycle costing is the total cost to the customer for the
acquisition and ownership over its full life. Life cycle costing
categories include the cost
of _____, _____, and _____.
A. R & D, maintainability, operation and support.
B. R & D, production, operation and support.
C. Acquisition, operations, maintenance.
D. Production, operations, maintenance.
E. None of the above
ANS: B
4. Management By Objectives assumes that the team:
A. is receptive to an unstructured environment.
B. does not require close supervision.
C. possesses a self directed philosophy
D. identifies with project objectives.
E. All of the above.
ANS: E
5. Quality may be defined as:
A. conformance to requirements.
B. fitness for use.
C. continuous improvement of products and services
D. appeal to the customer
E. All of the above except B
ANS: E
6. Since risk is associated with most projects, the best course of
action is to:
A. cover all project risks by buying appropriate insurance
B. ignore the risks, since nothing can be done about them and move
forward with the project in an expeditious manner.
C. avoid projects with clear and present risks
D. eliminate all known risks prior to the execution phase of the
project
E. identify various risks and implement actions to mitigate their
potential impact
ANS: E
7. The process of choosing/documenting the best approach to achieve
the project objectives is part of:
A. The scope baseline.
B. Scope authorization
C. Scope definition
D. Scope planning.
E. All of the above.
ANS: D
8. Time management is the allocation of time in a project’s life
cycle through the process of:
A. Planning
B. Estimating.
C. Scheduling.
D. Controlling
E. All of the above.
ANS: E
9. A comprehensive definition of scope management would be:
A. Managing a project in terms of its objective through the concept,
development, implementation, and termination phases of a project.
B. Approval of the scope baseline.
C. Approval of the detailed project charter.
D. Configuration control.
E. Approved detailed planning including budgets, resource allocation,
linear responsibility charts and management sponsorship.
ANS: A
10. Cost Plus Percentage of Cost contracts are more desirable for
the:
A. owner
B. buyer
C. seller
D. contractor
E. C or D
ANS: E
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 12015招标师考试项目管理考点:库存管理
- 2高层建筑的高程传递方法及精度分析
- 3一级建造师市政公用工程管理与实务复习要点:补偿器大集合
- 4国资委携84家央企齐聚保定助京津冀协同发展
- 5黄河上最宽的中央索面部分矮塔斜拉桥进入主梁期
- 6云南省2008年度安全工程师执业资格考试5月10日—6月10日网报
- 7造价工程师复习资料:在住宅小区规划设计中节约用地的主要措施
- 82015年安全工程师《相关法律知识》资料:检测检验机构的资质
- 9安全工程师安全生产法复习资料——烟花爆竹经营安全许可证
- 10安全工程师生产法复习资料——会审
- 11北京加强冬季施工绿色管理
- 122015年招标师考试:招标实务问答(78)
- 13项目决策分析与评价知识点:工艺技术转让的形式和方法
- 14名师达江解答二级建造师相关疑问——注册篇(一)
- 15无粘接力预应力筋
- 162012年一级建造师:建筑工程考点总结(1)
- 17安全文明:机具、材料管理
- 182015年注册咨询工程师《工程咨询概论》模拟试题(74)
- 19广州:农民依样建房可省数千元
- 202015招标师考试科目《项目管理》:招标采购项目的特点
- 21监理工程师应组织相关人员写出质量处理报告,其主要内容包括
- 22大跨径浅埋隧道长管棚施工工法
- 23工程造价基础:企业定额的作用
- 24某工程外墙综合防水施工方案
- 25安全工程师答疑荟萃:制度与职责
- 26我国政府职能转变促使社会多种中介服务发展
- 272015年咨询工程师《工程咨询概论》练习题13
- 28安全工程师答疑精华:反应式
- 292015年咨询工程师《工程咨询概论》每日一练8.21
- 30安全工程师生产法复习资料——安全评价机构违反有关安全评价规则
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼